A and B together can do a piece of work in 8 days, while B alone can finish it in 12 days. In how many days can A alone finish the work? |
|
Answer»
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work? [A]20 days [B]24 days [C]16 days [D]18 days 24 days A’s one DAY’s work = \FRAC{1}{12} (A + B)’s one day’s work = \frac{1}{8} ∴ B’s one day’s work = = \frac{1}{8} - \frac{1}{12} = \frac{3-2}{24} = \frac{1}{24} ∴ B alone can do the work in 24 days. Hence option [B] is the RIGHT answer.
|
|