| 1. |
A can do 2/3 of work in 16 days and B can do 1/4 of the same work in 3 days In how many can both finsh the work working together |
|
Answer» A can do 2/3 of work in 16 days and B can do 1/4 of the same work in 3 days In how many can both finsh the work working together |
|