A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work? |
|
Answer» LCM of 45 and 40 is 360. so let the work be of eating 360 chocolates. A finishes work in 40 days and B in 45 so A eats 9 chocolates per day and B eats 8 chocolates per day. together they work for 10 days and eat 17 chocolates each day. total chocolates eaten in 10 days=170. number of chocolates left=360-170=190 A will eat 190 chocolates in=>`190/9=21.1 days.` |
|