1.

a can do a piece of work in 8 days and b can do 10 days seperately how many days would it take for both a and b to finish the work together?​

Answer»

Answer:

A takes 8 DAYS to FINISH x amount of WORK.

B takes 10 days to finish x amount of work.

Work completed in 1 day by A=

8

x

Work completed in 1 day by B=

4

x

Work completed in 1 day by A and B =

8

x

+

4

x

=

8

3x

Days TAKEN to complete x amount of work by A and B =

work completed

x

=

8

3x

x

=

3

8

days