A city is going to install the rapid sand filter after the sedimentation tank. Use the following data:Design loading rate to the filter = 200 m3/m2/d ;Design now rate = 0.5 m3/sSurface area per filter box = 50 m2The surface area required for the rapid sand filter will be

Answer»

A city is going to install the rapid sand filter after the sedimentation tank. Use the following data:

Design loading rate to the filter = 200 m3/m2/d ;

Design now rate = 0.5 m3/s

Surface area per filter box = 50 m2

The surface area required for the rapid sand filter will be