1.

A Contractor employed 30 men to complete the project in 100 days. But later on he realized that just after 25 days only 20% of the work hadbeen completed. To complete the work on the scheduled time howmany men he has to increase?​

Answer»

-STEP EXPLANATION:HIII what are you doing