A If man cand do a work in 32 days.in how many days will 24 men complete the some work!​

Answer»

f allI wanna tell you that it is a problem of inverse variationSo the NUMBER of MAN increase and the number of DAYS decrease1*32=24*x32=24xx=32/24x==16/12x=8/6x=4/3men =32days =4/3