After A Change Has Been Implemented, An Evaluation Is Performed. What Is This Evaluation Called?

Answer»

It is known as POST Implementation Review (PIR) PIR is an assessment and review of the complete working solution. It will be PERFORMED after a period of live running, sometimes after the PROJECT is completed. The Post Implementation Review is used to evaluate the EFFECTIVENESS of system development after the system has been in production for a specific period (usually 6 months). It is a free­form report, and not all sections are relevant or necessary to the final product. A description of the Post Implementation Review Report is always attached.

It is known as Post Implementation Review (PIR) PIR is an assessment and review of the complete working solution. It will be performed after a period of live running, sometimes after the project is completed. The Post Implementation Review is used to evaluate the effectiveness of system development after the system has been in production for a specific period (usually 6 months). It is a free­form report, and not all sections are relevant or necessary to the final product. A description of the Post Implementation Review Report is always attached.



Discussion

No Comment Found