1.

Building of AIIMS Trauma Centre at Safdarjung Enclave in Delhi led to demolition of an unauthorised slum on that land a few years back. This is an example of :​

Answer»

Answer:

State-owned NBCC will be implementing the proposed project that will come up in an area of 60,500 square metre in the JPNATC campus-II at Safdarjung Enclave. The construction WORK is expected to be completed in four years.

In a letter to NBCC, Union environment MINISTRY said it has given the environment clearance to the AIIMS’ proposed project with CERTAIN riders.

The clearance has been given after taking into account the recommendations of an internal expert committee.

The land acquisition has been DONE for the proposed site. The COST of the project is estimated to be Rs 2,163 crore.

As per the proposal, the project will comprise of constructing five blocks with 184 beds. Maximum height of the building will be 38 metre.