"change Estimated Costs On A Cs Order" i Have Read From Previous Posts That It Is Not Possible In Standard Sap To Change The Estimated Costs For Released Service Orders. has There Been A System Modification Implemented To Change This And Make It Possible? What Do You Have To Change To Enable The User Exit? |
|
Answer» i Have Read From Previous Posts That It Is Not Possible In Standard SAP To Change The ESTIMATED Costs For RELEASED Service Orders. has There Been A System Modification Implemented To Change This And Make It Possible? What Do You Have To Change To Enable The User Exit? You cannot change the estimated costs once the ORDER is released. But I believe that it is possible via a “direct database update”. COORDINATE the task with your ABAP team as they are in a position to help. You cannot change the estimated costs once the order is released. But I believe that it is possible via a “direct database update”. Coordinate the task with your ABAP team as they are in a position to help. |
|