Different expenditures incurred on the construction of a building were shown by a pie diagram. The expenditure rs 45,000 on cement was shown by a sector of central angle of `75^@` . What was the total expenditure of the construction ?A. 2,16,000B. 3,60,000C. 4,50,000D. 7,50,000 |
Answer» Correct Answer - A | |