Does a Product Owner have the authority to replace an item in the Sprint Backlog?

Answer»

No. The Sprint BACKLOG is the representation of the tasks that are drawn from the product backlog to achieve the Sprint goal by the development team.  During the Sprint Planning, the development team SETS an objective which is CALLED as a Sprint goal. Only the development team can MAKE changes to the Sprint Backlog as they own it. None changes can be made without the AUTHORIZATION of the development team members.