During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?

Answer»

The Product OWNER and the Development Team. During the Sprint, the scope may be clarified and renegotiated between the Product Owner and Development Team as more is learned. As ISSUES EMERGE, changes can be made to the sprint backlog to accomplish the Sprint GOAL. The Development Team will then re-negotiate with the Product Owner REGARDING the Sprint Backlog. Although the Sprint Goal is fixed during the Sprint, the Sprint Backlog is not.