During daily scrum, which plan is used as a reference to understand the change in progress?

Answer»

Sprint backlog.Team members are expected to update the sprint backlog at least once a day during the SCRUM sprint as new information is available. Most of the scrum teams will do this during the Daily Scrum. Scrum master ESTIMATES the amount of work remaining in the sprint each day and graphs the sprint burndown CHART. The sprint backlog is a plan with ample detail that changes in DEVELOPMENT can be understood in the Daily Scrum.