| 1. |
Explain What Is The Use Of Work Contour In Ms Project? What Are The Different Types Of Contour You Use In Ms Project? |
|
Answer» In MS project work, CONTOUR displays the distribution of WORKING hours over the duration of the task.The graph will SHOW the peak according the work distribution over the week. Flat: Such contour signifies an even distribution of work Back-loaded: It will show the peak activity at the end of the project Front-loaded: It will show the peak working activity at the OPENING of the project Double peak: It will show two major periods of peak activity Early peak: It is same as the front loaded but with the rise to peak activity Late peak: It is same as a back loaded contour with a ramp BELL: It shows a single peak in the central of the project Turtle: A bell with a ramp up and down In MS project work, contour displays the distribution of working hours over the duration of the task.The graph will show the peak according the work distribution over the week. Flat: Such contour signifies an even distribution of work Back-loaded: It will show the peak activity at the end of the project Front-loaded: It will show the peak working activity at the opening of the project Double peak: It will show two major periods of peak activity Early peak: It is same as the front loaded but with the rise to peak activity Late peak: It is same as a back loaded contour with a ramp Bell: It shows a single peak in the central of the project Turtle: A bell with a ramp up and down |
|