Mention The Sorts Of Task Links In Ms Mission 2013?

Answer»

There are four forms of TASK LINKS in MS mission:

  • Finish to begin link: in this link, the second VENTURE cannot be initiated till the first task is FINISHED.
  • Begin to begin hyperlink: in this hyperlink, the second task can start at any time after the first assignment is initiated.
  • End to complete hyperlink: in this link, the mission does no longer should stop at the same time, the second challenge can quit EVERY time after the first venture is ended.
  • Start to finish link: on this hyperlink, the second mission can’t finish until the first task begins.

There are four forms of task links in MS mission: