Final setting time of cement should not be more than _______(a) 1 hour(b) 2 hours(c) 5 hours(d) 10 hoursThe question was asked by my school principal while I was bunking the class.This interesting question is from Setting Time Test in portion Types of Cement and Testing of Cement of Concrete Technology

Answer»

Correct OPTION is (d) 10 hours

To explain I would SAY: As per IS SPECIFICATION, the MAXIMUM final SETTING time for all type of cement is 10 hours.