Initial setting time of Low Heat Cement should not be less than _____________(a) 15 minutes(b) 30 minutes(c) 60 minutes(d) 1 hourThe question was asked in an online quiz.My query is from Setting Time Test in section Types of Cement and Testing of Cement of Concrete Technology

Answer»

The CORRECT option is (c) 60 minutes

Explanation: As PER IS specification, the minimum INITIAL SETTING time is 60 minutes for low heat cement.