For projects which have multiple teams, how many product backlog(s) and product owner(s) should be there? |
|
Answer» There should be one Product Backlog and one Product Owner. Many SCRUM teams, each with a Scrum Master can pull work items from a single product backlog and the presence of the product OWNERS depend on the number of product backlogs. A CERTAIN project should have only one Product Backlog and one Product Backlog should only have one Product Owner otherwise, it WOULD be difficult to DELIVER the product. |
|