For projects which have multiple teams, how many product backlog(s) and product owner(s) should be there?

Answer»

There should be one Product Backlog and one Product Owner. Many SCRUM teams, each with a Scrum Master can pull work items from a single product backlog and the presence of the product OWNERS depend on the number of product backlogs. A CERTAIN project should have only one Product Backlog and one Product Backlog should only have one Product Owner otherwise, it WOULD be difficult to DELIVER the product.