| 1. |
For the schedule given below, which of the following is Correct?1 Read A2 Read B3 Write A4 Read A5 Write A6 Write B7 Read B8 Write B (A) This schedule is serialisable and can occur in a scheme using 2PL protocol.(B) This schedule is serialisable but cannot occur in a scheme using 2PL protocol.(C) This schedule is not serialisable but can occur in a scheme using 2PL protocol.(D) This schedule is not serialisable and cannot occur in a scheme using 2PL protocol. |