1.

Given the complex product and its relevance to multiple departments, a Scrum Team expects that they need to invite many stakeholders for Sprint Review. It estimates that the review will take more than 4 hours. Can it increase the Sprint review duration?

Answer»

No. After developing a product increment at the END of each sprint, a Sprint REVIEW meeting is held. The Sprint Review meeting provides a platform to the team MEMBERS to show what they accomplished during the sprint. Scrum EVENTS are time-boxed to eliminate waste and reduce risks. The team needs to address the root causes and ADHERE to the time-box.