How Can We Assign Measuring Points To A Strategy Plan Like Compressor Running Hrs? |
|
Answer» Go to the CHANGE EQUIPMENT transaction , then extra, then add or replace counters. then SELECT the desired counter by F4 help. you can't DIRECTLY add counters or measuring PTS to a maintenance plan. u can do this for equipment , FL and PRT only. Go to the change equipment transaction , then extra, then add or replace counters. then select the desired counter by F4 help. you can't directly add counters or measuring pts to a maintenance plan. u can do this for equipment , FL and PRT only. |
|