How many times in each layer of concrete rodded in a slump cone?(a) 75(b) 25(c) 12 to 15(d) 35 to 65I got this question during an online interview.My question comes from Testing of Cement topic in division Types of Cement and Testing of Cement of Concrete Technology

Answer»

Correct OPTION is (B) 25

Easy explanation: Each TIME, each layer is tamped 25 times with a 2 ft (600 mm)-long bullet-nosed METAL ROD measuring 5/8 in (16 mm) in diameter.