1.

How Project Accounting Interacts With Purchasing Module?

Answer»
  • Project related Purchase Orders are created in Oracle Purchasing module. This is a cost against the project and hence has to be transferred to oracle PROJECTS.

There are 2 ways to do this.

  1. CREATE a Supplier invoice against the PO. Then interface the supplier invoice to projects module.
  2. In-case when we cannot WAIT for an invoice to be created, we will have to transfer the PO cost directly to projects. This can be DONE by creating a Purchase receipt against that PO. Then interface the receipts directly to projects module.
  • To interface the Purchase Receipts, PRC: Interface Supplier Costs PROCESS can be run. This process fetches all the receipts matched against the project related PO.
  • Receipt distributions are interfaced to projects module as expenditure items.