1.

How To Order Lafarge Readymix Concrete?

Answer»

Procedure

  • Concrete can be ordered telephonically via our central orders department in the various regions
  • Place orders at least 24 hours in ADVANCE
  • Confirm your order by 12h00 the day before delivery
  • All account customers must fax an OFFICIAL order number to our Central Orders Department
  • Same day orders will be accommodated if our delivery schedule allows it and the available time is suitable for the customer’s needs
  • Special concrete mix requirements can be met, subject to the outcome of trials in our labs by our technical team
  • When placing orders, customers will be asked about the application as well as the strength of concrete they require
  • If help is required to specify the concrete mix design, please contact the local Lafarge Technical Department

After Hours and Weekend Deliveries

  • After hours pours should be arranged with the Lafarge District Sales Manager
  • After hours pours will incur extra costs
  • Requirements for pours on Sundays should be discussed with the Lafarge Districts Sales Manager
  • SUNDAY deliveries will also incur extra costs

Cancellations

  • Cancellations for concrete orders must be done by 15h00 at the latest on the day prior to the pour
  • Late cancellations will incur extra cost. If the concrete has been loaded before cancellation, the customer
  • will be charged for the full load of concrete

Payments

  • Orders being paid for in cash will only be confirmed once payment has been received
  • Payments by cheque to the value of R5000 and over must be bank guaranteed
  • INTERNET payments must be done at least 48 hours in advance
  • Customers should fax the proof of payment through to the Lafarge Central Orders Department at least four WORKING hours before dispatch of the order is required

Part Load Charges:  Loads less than 3m3 will attract a part load charge

Pumping

  • The Lafarge concrete pumping service needs to be booked one week in advance
  • At least 24 hour notice should be given to cancel a pump booking. Cancellation of a pump on the same day will incur a cancellation fee

Quality Control: Lafarge Technical Department conducts random quality control testing on all Readymix concrete that is supplied

Procedure

After Hours and Weekend Deliveries

Cancellations

Payments

Part Load Charges:  Loads less than 3m3 will attract a part load charge

Pumping

Quality Control: Lafarge Technical Department conducts random quality control testing on all Readymix concrete that is supplied



Discussion