If 36 workers can do a piece of work in 20 days, in how many days 64 workers can do same work? |
|
Answer» Step-by-step explanation: workers and days are INVERSELY proportional. so FORMULA is M1*D1=M2*D2 36×20=64×D2 D2 = 36×20/64=10 days |
|