If ₹42,000 is spent on wages of 12 men working for 30 days, then what amount would have been spent if there were 18 men working for 24 days?50400

Answer» If ₹42,000 is spent on wages of 12 men working for 30 days, then what amount would have been spent if there were 18 men working for 24 days?
  1. 50400