if 45 aceres of plot are dug by 40 men in a day,how many men will be required to dig 72 acers of plot in a day |
|
Answer» Answer: 72 acres - 'X' men we need to FIND 'x' x = 72 × 40 DIVIDE by 45 = 2880 ÷ 45 = 65 men's X is '45 mens' . Thankyou |
|