if 80 men can dig a well in 10 days. after they have worked for 4 days, how many more men shall be employed to complete the work in 4 days from then.​

Answer»

Step-by-step EXPLANATION:

MEN Days

80 10

× 4

therefore x=80×4/10

8×4=32 more men should be EMPLOYED