If m persons can complete a work in n days, then 4m persons can complete the same work in ……….. days and m/4 persons can complete the same work in…….. days. |
|
Answer» Given m persons complete a work in n days (i) Then work measured in terms of Man days = mn 4 m men do the work it will be completed in mn/4m days = n/4 days. (ii) m/4 persons can complete the same work in mn/m/4 days = 4mn/m = 4n days |
|