In the given tank, there are two feeds and one output. Consider a 2 hour operation; the feed rates are 4000 kg/hr and 6000 kg/hr. The accumulated material inside the tank is 2000 kg. What is the output rate kg/hr of the material?(a) 9000(b) 8000(c) 7000(d) 6000I had been asked this question by my school teacher while I was bunking the class.Question is from Material Balances -I in division Material Balances of Chemical Process Calculation

Answer»

The CORRECT ANSWER is (a) 9000

Explanation: INPUT = output, TAKE a basis: 2 hour.