Should each Sprint Backlog item be owned by a member of the Development Team?

Answer»

No. Single members MIGHT handle most or all of the work of a particular Sprint BACKLOG item, but RESPONSIBILITY remains for the WHOLE team. When each member of the Development team owns the Sprint Backlog items, the team will DERAIL from the core-value of Agile which is nothing but the ‘Collaboration’.