Saved Bookmarks
| 1. |
Ten men working 6hours a day take 12days to complete a job. How long will it take 8men working 12hours a day to complete the same job :^.^ |
|
Answer» Answer: LET the day be x then, (10×6×12)/(8×12×x) 720/96x x = 720÷48/96÷48 (48 as HCF) x= 15/2 x= 7 1/2 days || keep learning || |
|