The Perform Integrated Change Control Process Includes Several Configuration Management Activities. Which Of The Following Is Not A Configuration Management Activity?

Answer»

Change request is not a VALID response. The CONFIGURATION management activities INCLUDED in the Perform Integrated Change CONTROL PROCESS are: Configuration Identification, Configuration Status

Change request is not a valid response. The configuration management activities included in the Perform Integrated Change Control process are: Configuration Identification, Configuration Status