Which Of These Is Not An Approved Estimate Activity Durations Technique?

Answer»

Analogous, PARAMETRIC, and three-point estimating TECHNIQUES are all accepted practices for determining the correct amount of TIME required for a portion of the project. The CRITICAL Path Analysis techniques evaluate the WHOLE project schedule.

Analogous, parametric, and three-point estimating techniques are all accepted practices for determining the correct amount of time required for a portion of the project. The Critical Path Analysis techniques evaluate the whole project schedule.