| 1. |
The prestressing force in the tendon is 1200 kN, acting on a beam section of 400 mm × 600 mm. Span of the beam is 6 m and carries an all inclusive load of 40 kN/m. If the profile of the beam is as per load balancing cable for the beam then the cable should be provided with a central dip of _____ mm.150 |
Answer» The prestressing force in the tendon is 1200 kN, acting on a beam section of 400 mm × 600 mm. Span of the beam is 6 m and carries an all inclusive load of 40 kN/m. If the profile of the beam is as per load balancing cable for the beam then the cable should be provided with a central dip of _____ mm.
|
|