Threeman a b and c complete the work 15 12 and 10 days a b and c starts work together but c left the work after 2 days and b left the work 3 days before the completion of the work howin how much time the whole work will be completed |
|
Answer» Answer: The whole work will be completed in 6.33 DAYS. Explanation: A's one day work = 1/15 B's one day work = 1/12 C's one day work = 1/10 (A+B+C)'s one day work = 1/15 + 1/12 + 1/10 = 4 + 5 + 6 / 60 = 15/60 = 1/4 (A+B+C)'s two day work = 1/4 × 2 = 1/2. By condition, C left the JOB in two days. Hence, REMAINING work = 1 - 1/2 = 1/2 Let the whole work be done in x days. (A+B)'s one day work = 1/15 + 1/12 = 4+5 / 60 = 9/60 = 3/20 (A+B)'s x-3 day work = 3/20 × x-3 = 3x - 9 / 20 Remaining work = 1/2 - 3x-9/20 = 10 - (3x-9) / 20 = 10 - 3x + 9 / 20 = 19 - 3x / 20 Time taken by A to complete the remaining work = 19 - 3x / 20 × 15 = 19 - 3x / 4 × 3 = 3(19 - 3x) / 4 = 57 - 9x / 4 By condition, 1/2 + (3x - 9 / 20) + (57 - 9x / 4) = 1 => (3x - 9 / 20) + (57 - 9x / 4) = 1 - 1/2 => (3x - 9) + 5(57 - 9x) / 20 = 1/2 => 3x - 9 + 285 - 45x / 20 = 1/2 => 3x - 45x + 285 - 9 / 20 = 1/2 => - 42x + 276 = 1/2 × 20 = 10 => - 42x = 10 - 276 = - 266 => 42x = 266 => x = 266/42 = 6.33 (ans). KINDLY SELECT MY ANSWER AS THE BRAINLIEST ANSWER. |
|