To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it? (a) 30 days (b) 35 days (c) 40 days (d) 45 days |
|
Answer» To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it? (a) 30 days (b) 35 days (c) 40 days (d) 45 days |
|