What are the different currency type in SAP PS system?

Answer»

In SAP PS system, you can manage all the currency dependent data in the Project System using below different currencies.

Controlling area currency

In this currency type, you define work breakdown structure WBS, networks, activities, and orders in one controlling area.

As same controlling area is used, currency in a project system is also uniform.

Object Currency

In Project system, it is also possible to assign any object currency to different objects in the system.

  • WBS element
  • Project definition
  • Network header
  • Network activity

Note that when a company code is assigned to a controlling area and company code contains multiple currencies in this case you can’t allocate object currency in PS as in this case system automatically takes the local currency of company code.

Transaction Currency

In this case, you use the costs and revenues from different business transactions are recorded as per currency of the business transaction.