Answer» Agile PLANNING is iterative in nature. Planning Stage
| Description
| Ownership
| Frequency
|
|---|
Product Vision
| To detail what the product is, who will and why use it, and how the product supports the COMPANY’s overall strategy
| Product Owner
| Revised once a year
| Product Roadmap
| To provide a visual overview of the high-level product requirements, timeframes for deliverables, prioritization and estimations details of all releases over time
| Product Owner
| Revised twice a yea
| Release Plan
| To describe the high-level timeline for product releases
| Product Owner
| Revised twice/four times a year
| Sprint Plan
| To describe sprint goals and requirements and how those requirements will be COMPLETED
| Project Team
| Revised once a sprint
| Daily Scrum
| To discuss on what was completed YESTERDAY, what will be done today and any roadblocks found
| Project Team
| Daily for 15 minutes
| Sprint Review
| To demonstrate the working product/deliverable to stakeholders for feedback/acceptance
| Project Team
| Monthly, or at least for each sprint, for an hour
| Sprint Retrospective
| To discuss on product and process improvements and picking on at least one area to focus on continuous improvement
| Project Team
| Monthly, or at least for each sprint, for an hour
|
|