What is a sprint planning meeting?

Answer»
  • Attendees: Development team, Scrum Master and Product Owner
  • When: At the beginning of the sprint.
  • Duration: Approx 4 HOURS for a 2-week iteration
  • Purpose: Product owner COMES with the prioritized backlog and then the Scrum Team plans the items they are GOING to deliver in the Sprint and the way they will deliver them, estimate them, break into TASKS. The team can ask questions to the product owner about the user STORIES if they didn’t understand properly.