Answer» RUN LIMIT property sets the HIGHEST number of jobs of the project that are allowed at one time.
- When we launch a project and the active jobs equal to the Run Limit, then the latest job stays in the QUEUE until the other one completes.
- When a schedule attempts to initiate a project and the active jobs equal the Run Limit with the Hard Run Limit system set up has a value of Yes, then the system does not initiate the NEW job. If only the Hard Run Limit is set to No, the system ignores the Run Limit set up for any scheduled builds.
- Projects which are initiated through an Inline chain are not considered for instances of the primary project and do not count to its Run Limit.
Run Limit property sets the highest number of jobs of the project that are allowed at one time.
|