1.

What Is Setup And Hold Time Violations?

Answer»

VIOLATING above setup and HOLD time requirements is called setup and hold time violations. If there is setup and hold time violations in the design does not meet the TIMING requirements and the functionality of the design is not reliable. STA CHECKS this setup and hold violations.

Violating above setup and hold time requirements is called setup and hold time violations. If there is setup and hold time violations in the design does not meet the timing requirements and the functionality of the design is not reliable. STA checks this setup and hold violations.