What Is The Formula Used For Calculation Of Labour Rate Variance Is?

Answer»

The FORMULA used for calculation of labour rate variance is:

(STANDARD rate per HOUR - ACTUAL rate per hour) * Actual Hours

The formula used for calculation of labour rate variance is:

(Standard rate per hour - Actual rate per hour) * Actual Hours