What is the importance of Sprint 0?

Answer»

Sprint 0 is a concept that team needs some time to settle down before delivering actual value to the customer from sprint 1. But it has been misused a lot LATELY as an excuse to put everything in place then go for sprints. So essentially, the misuse is LIKE doing waterfall in Agile projects.

The correct way of doing sprint 0 is when the REQUIREMENTS are very VAGUE that no user story can be started off or the TECHNOLOGY is completely new for the team or the project is so complex that there needs to be a dedicated time for product discovery. In such cases, sprint 0 should be allowed where team resolves these issues and is not bound to deliver any value.