What Is The Utility Of Work Contouring In The Software? Name The Different Types Of Contouring That Are Used In The Ms Project.

Answer»

A Project MANAGER needs to know the spreading of the work HOURS during the week. This is facilitated by the work contouring feature of the software. It shows you a graph according to the distribution of the work in the week.

  • A flat contour shows evenness in the distribution of work in the week.
  • The peak of activity at the end of the project is shown by the back loaded OPTION.
  • The peak of activity at the beginning of the project is shown with the front loading option.
  • There are only two major peaks in the project known as DOUBLE peaks- once in the beginning and one at the end.
  • When the activity rises at a peak at the earliest in the project, it is known as the early peak.
  • When the same thing as back loading COMES with a ramp, it is known as the late peak.
  • The singular peak in the middle of the project is known as bell.
  • When there is both ramps down and up in a bell, it is known as a turtle.

A Project manager needs to know the spreading of the work hours during the week. This is facilitated by the work contouring feature of the software. It shows you a graph according to the distribution of the work in the week.