What pre-conditions must be fulfilled in order to allow Sprint Planning to begin? |
|
Answer» There are no such pre-conditions. Sprint Planning serves to plan the work to be performed in the Sprint. This plan is created by the COLLABORATIVE work of the entire SCRUM Team. Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. What can be achieved in this time-box may be INFLUENCED by additional practices that are HOWEVER not PRESCRIBED by Scrum. |
|