1.

What Value Combinations For Max Job, Flow Limit & Use Activation Limit Will Executes The Processes In A Sequential Manner?

Answer»
  • Max Job=1, USE Activation Limit= CHECKED, FLOW Limit=N
  • Max Job=1, Use Activation Limit= Checked, Flow Limit=0

Note:above SETTINGS will CREATE a lot of overhead, if you want to achieve the sequential execution a better way is to define the Sequencing key on the Misc. tab of the Process starter palettes.

Note:above settings will create a lot of overhead, if you want to achieve the sequential execution a better way is to define the Sequencing key on the Misc. tab of the Process starter palettes.



Discussion

No Comment Found