1.

When 25 men work 2 hours per day for 28 days they produce 1200 units. if 15 men work 9 hours per day then in how many days will they produce 1500 units

Answer»

Answer:

25 MEN working 2 hrs / DAY can do a piece in 28 DAYS

∴ Total work units =25×2×28

=1400

No.of days required by 15 men, working at

a hrs/day=

15×9

2880

16 days