1.

Which of the following activities belong to project closing process group? A Index and archive the project records. B Facilitate conflict resolution. C Inform stakeholders about project completion. D Hold a final meeting with project team.

Answer»

ANSWER:

The inputs to the Close Project or PHASE PROCESS are project MANAGEMENT plan, ACCEPTED deliverables, and organizational process assets.